If a project finishes ahead of schedule, follow these steps to reflect it accurately in Airtable:

  1. Update the Timeline:

    • Adjust the project timeline to reflect the updated dates and when tasks were actually completed.

  2. Rename the Final Task:

    • Edit the title of the final task to include a note, such as Finished Ahead of Schedule, to indicate the early completion.

  3. Document the Original Deadline:

    • Manually add a new one-day task to the timeline on the original completion date.

    • Name this task Original Deadline to visually distinguish it from the actual delivery date.

This method provides clear documentation of both the original deadline and the updated, ahead-of-schedule completion date.